Performance Analysis

Performance analysis (2016)

ECOSESTO Spa asked to W.T.E. to conduct an audit on energetic performance of the biomass to energy plant (16.5 MWe) operating in Rende(Calabria) in order to improve the energy efficiency of the plant. W.T.E.’ aim was to achieve the optimisation of combustion process through increased flexibility; the final aim was to allow the combustion of

Performance analysis (2016) Read More »

Assessment of the solar thermal input to the electricity’s amount supplied by biomass plant (2016)

ECOSESTO SpA  appointed W.T.E. to assess the contribute of solar heat supplied to a conventional Rankine cycle in terms of delivered electric energy . A proper evaluation was required in order to obtain the corresponding fee from GSE, Italian energy Authority. Considering the inertion of solar heat at lower  temperature than those used in biomass

Assessment of the solar thermal input to the electricity’s amount supplied by biomass plant (2016) Read More »