A preview of the work we’ve completed over 25 years, demonstrating our engineering and sustainable approach.
From design to construction, each project demonstrates our commitment to innovation and the ecological transition.
W.T.E. is committed to study and project a new gas recirculation system to up grade the existing the combustion control system.
Read more
System functional testing of the efw plant.
The Owner of a textile industrial firm needs a feasibility study of a new boiler and its gas cleaning system. The CHP installed and operating giving power to the production process is fed by biomass; W.T.E. was appointed to enhance the performances of the combustion and of the emissions of gases consequentlly. The study offers […]
Investanas JSC (Vilnius) has assigned W.T.E. Waste to Energy Srl to design a complete incineration plant, including the basic and detailed design of a furnace-boiler system (tail-end type), a flue gas cleaning system, a fly ash handling and storage system, and all other auxiliary systems. Main data: 11,5 MWth capacity 100 % MCR; LHV from […]
Assignment for the design of a system for the drying of organic sludge (110,000 t/y) and their combustion to be implemented within the area of the old waste-to-energy plant located in Ca’ del Bue.
Support and direct drafting of all the documents required by law in order to obtain the review of the authorisation (A.I.A. Italian document) of the operating WtE plant (expertise, review overhaul and complement of documentation, compliance with the BAT). New design of the pumping station of the water feeding system.
Feasibility study of a new co-incineration plant to be installed in the industrial area.
The basic engineering of a new CHPP 4MWt+3MWt was to include the study of the energetic optimization of the thermal sources available to the company and the project of the distribution of the heat within theinternal industrial network.
Consulting to get INAIL approval for the revamping of the pressure parts modification of three utility boilers installed on the Ilva steel mill plant (Taranto) in the ambit of the delivery of three new gas cleaning systems.